You are browsing the archive for Oracle Engineering.

5. Engineering Change Order Priorities Report

Report Short Code: ENGRDECP

Report Name: Engineering Change Order Priorities Report

Module: Oracle Engineering

Report Summary: Engineering Change Order Priorities Report prints all the priorities setup in Oracle Engineering.

Navigation:

Engineering -> Reports -> Setups -> Select Report Name as ‘Engineering Change Order Priorities Report’

 

Engineering Change Order Priorities Report

Engineering Change Order Priorities Report

 

Report Parameters

This report has no paramters.

 

Report Output:

Report displays all the setups defined for ECO Priorities.

Engineering Change Order Priorities Report Output

Engineering Change Order Priorities Report Output

4. Engineering Change Order Approval Lists Report

Report Short Code: ENGRCOAL

Report Name: Engineering Change Order Approval Lists Report

Module: Oracle Engineering

Report Summary: Engineering Change Order Approval Lists Report prints all the approval lists setup in Oracle Engineering.

Navigation:

Engineering -> Reports -> Setups -> Select Report Name as ‘Engineering Change Order Approval Lists Report’

Engineering Change Order Approval Lists Report

Engineering Change Order Approval Lists Report

 

Report Parameters

  • Approval List From
  • Approval List To

 

Report Output:

Report displays the ECO approval lists setup in Oracle Engineering.

Engineering Change Order Approval Lists Report Output

Engineering Change Order Approval Lists Report Output

3. Engineering Change Order Schedule Report

Report Short Code: ENGRCNSR

Report Name: Engineering Change Order Schedule Report

Module: Oracle Engineering

Report Summary: Engineering Change Order Schedule report prints the detail schedule pending ECO implementations based on scheduled implementation date of a given revised part.

Navigation:

Engineering -> Reports -> ECOs -> Select Report Name as ‘Engineering Change Order Schedule Report’

Engineering Change Order Schedule Report

Engineering Change Order Schedule Report

Report Parameters

  • Print components
  • Engineering Change Order Type
  • Engineering Change Order From
  • Engineering Change Order To
  • Effective Dates From
  • Effective Dates To
  • Revised Item Status
  • Display Option
  • Revised Item
  • Revised Component
  • Sort Criteria1
  • Sort Criteria2
  • Sort Criteria3

 

Report Output:

Report displays the schedule of ECO implementations for a revised part.

Engineering Change Order Schedule Report Output

Engineering Change Order Schedule Report Output